Completed: 2016
Ready For Immediate Occupancy

Think of the Meatpacking District in Manhattan, Soho in London or Omotesando in Tokyo. Think cool and fashionable. Think dynamic and unique.

Taking inspiration from the vibrant districts of capitals around the globe, The Lofts Ekkamai’s industrial attic rooms are a mix of smooth design, effortless functionality and artistic beauty. With a warehouse-style inspiration, you’ll enjoy ample space with floor-to-ceiling glass illuminating your life, giving you an unobstructed window to the scintillating city skyline.

Spacious external living areas permit your own unique and spectacular view. Interiors crafted with exceptional materials ensure the life you lead is unique, comfortable and hip.

 

Tenure:

Type:

Storeys:

Units:

Format:

Main Contractor Commencement:

Construction Completion:

Primary Construction Co.:

Primary Design Co.:

Freehold

Condominium

28 (single tower)

263 (approximately)

1-3 bedrooms, lofts

2014

2016

Ritta Co., Ltd.

HB Design Pte Ltd.

 

Contact Us

The Lofts Ekkamai Sales Office

Sukhumvit Road between sois 63-65

Phra Kanong Nua, Wattana, Bangkok 10110

 

Tel: (+66) 2 651 9600
Email: direct.marketing@raimonland.com

 

Location: Bangkok
Map:
Site Location:

The Lofts Ekkamai
Sukhumvit Road between sois 63-65
Phra Kanong Nua, Wattana, Bangkok 10110

Website: www.theloftsekkamai.com

Contact Us


Construction Update 18 Feb 2016

Structure Works = 100% completed.
 
Architecture Works = 86% complete.

  • Internal wall and partitions = completed.
  • Internal plastering and skim coat = completed.
  • Ceiling closure = completed.
  • Tiling works = up to 26th floor.
  • Door frame and door panels = up to 19th floor.
  • Kitchen cabinets and joinery works - up to 18th floor
  • Aluminium facade, Aluminium doors and windows = completed.

 
MEP Works = 81% complete

  • Mechanical works = completed.
  • Electrical works = completed.
  • Plumbing works = completed.
  • Air-conditioning works = up to 23th floor.
  • Passenger and fireman lift car installation = up to 70%.
  • Permanent utilities connection = 20% complete
  • MEP testing and commissioning = up to 7th floor.